At 6 a.m. on Monday, September 30, NV Energy will resume work on Highway 50 in Stateline at South Lake Tahoe with new measures in place for traffic flow.

The work is to replace equipment in two underground electric vaults.

The new traffic plan will be in effect 6 a.m. Monday, Sept. 30 through approximately 5 p.m. Friday, Oct. 4:

-One lane of traffic will be open in each direction on Highway 50 through the casino corridor.
-Additionally, traffic may also take Lake Parkway for additional business access.-
-Westbound through traffic that takes Lake Parkway may continue to Park Avenue and then back to Highway 50.
-Eastbound through traffic that takes Heavenly Village Way may continue to Lake Parkway then back to Highway 50.
-The road will be open to its normal traffic pattern starting Friday at approximately 5 p.m. throughout the weekend.
-During the week of Oct. 7, minor lane restrictions will continue.

The work is being done for safety and increased reliability. The project, including excavation and repaving, is estimated to be completed on October 11. The schedule is subject to change based on weather. During this time, NV Energy will work closely with the Nevada Department of Transportation (NDOT) regarding road closures.

NV Energy to resume work on Highway 50 with new traffic plan PDF

Highway 50 lane closure map PDF

 

The safety of our customers, our employees, and our electric system is NV Energy’s number one priority. Due to changes in our climate and our environment, extreme weather and wildfire pose a significant threat to our customers and our system. To protect high-risk communities including Mt. Charleston and Lake Tahoe during extreme weather, NV Energy may shut off power for public safety in order to reduce the risk of a wildfire. This is called Public Safety Outage Management (PSOM).

 